FINAL REPORT

VOLUME III OF VII TOPOGRAPHIC AND BATHYMETRIC SURVEY

MISSISSIPPI RIVER RE-INTRODUCTION INTO MAUREPAS SWAMP PROJECT PO-29

Louisiana Department of Natural Resources U.S. Environmental Protection Agency

October 2005 URS Corporation Evans-Graves Engineers, Inc. 3001, INC.

TABLE OF CONTENTS Section 1

Introduction .............................................................................................................. 1-1

Section 2

Review of Existing Data and Planning ................................................................... 2-1

Section 3

Channel Cross Sections South of US Highway 61................................................ 3-1

Section 4

Channel Cross Section North of US 61/South of I-10 ........................................... 4-1

Section 5

Channel Cross Sections North of I-10.................................................................... 5-1

Section 6

Crossing and Culvert Surveys................................................................................ 6-1

Section 7

Additional Channel Bathymetry.............................................................................. 7-1

Section 8

Additional Embankment Topography .................................................................... 8-1

Section 9

Swamp Topography................................................................................................. 9-1

Section 10

Data QC and High Resolution Digital Terrain Model........................................... 10-1

I:\Projects\LDNR\10001073-Maurepas Diversion\Reports-Working\V3 Topo & Bath Survey\Topographic and Bathymetric Survey Report.doc \9-AUG-07\BTR

i

TABLE OF CONTENTS TABLES Table 1 Table 2

Summary of Channel Geometry in Central and North Areas ........................ 4-2 List of Significant Swamp Linear Features ................................................. 10-3

FIGURES Figure 1 Figure 2 Figure 3

Topographic and Bathymetric Survey Locations South of US Highway 61 Topographic and Bathymetric Survey Locations North of US Highway 61 LIDAR Data North of US Highway 61

APPENDICES Appendix A Appendix B Appendix C Appendix D Appendix E Appendix F Appendix G Appendix H Appendix I

Pyburn and Odom Project Area Cross Section Data Channel Cross Sections South of US Highway 61 Channel Cross Sections North of US Highway 61 Channel Cross Sections North of Interstate 10 Crossings and Culverts Surveys Additional Channel Bathymetry Additional Embankment Topography Additional Swamp Topography CD Copy of Report

I:\Projects\LDNR\10001073-Maurepas Diversion\Reports-Working\V3 Topo & Bath Survey\Topographic and Bathymetric Survey Report.doc \9-AUG-07\BTR

ii

SECTIONONE Section 1

ONE

Introduction

Introduction

The topographic and bathymetric survey work was undertaken in support of the Hydraulic Feasibility Study for the Mississippi River Re-Introduction into Maurepas Swamp Project (PO-29). Volume II, Secondary Benchmark GPS Static Survey (URS Corporation, April 2005) has previously been submitted which documents the establishment of project survey monuments tied to the LDNR Primary Network. The topographic and bathymetric survey work was divided into nine activities: • • • • • • • • •

Review of Existing Data and Planning Channel Cross Sections South of US 61 Channel Cross Sections North of US 61/South of I-10 Channel Cross Sections North of I-10 Crossing and Culvert Surveys Additional Channel Bathymetry Additional Embankment Topography Swamp Topography Data QC and Development of High Resolution Digital Terrain Model

This Volume describes methodologies (including quality control review) and presents results for field topographic and bathymetric surveys. Tabulated data for the surveys are included in Appendices A through H, and a digital copy of the field data and GIS files is attached in Appendix I. In addition, to presenting the data, this Volume summarizes key findings and describes the development of a very detailed Digital Terrain Model of the project area north of US Highway 61. The DTM uses nearly 2.5 million vertices and encompasses 175 miles of linear features.

I:\Projects\LDNR\10001073-Maurepas Diversion\Reports-Working\V3 Topo & Bath Survey\Topographic and Bathymetric Survey Report.doc \9-AUG-07\BTR

1-1

SECTIONTWO Section 2

TWO

Review of Existing Data and Planning

Review of Existing Data and Planning

Information from several sources was gathered and studied as part of the survey planning, including: •

Diversion into the Maurepas Swamps, A Complex Project under the Coastal Planning, Protection, and Restoration Act, Lee Wilson & Associates, June 2001.



Surveys for Establishing 24 Proposed Staff Gages, Pyburn and Odom, Inc., August 2000; (Cross section data is presented in Appendix A).



High resolution (pixel size <1ft), rectified Color-IR imagery of the project area, for LDNR by Gulf Coast Aerial Photography, March 2003.



Survey of Major Channel Bank Gaps, Louisiana State University, JulyAugust, 2000.



Light Detection and Ranging (LIDAR) data, for the Louisiana Oil Spill Coordinators Office by 3001, Inc., March 3, 1999 and March 5 and 6, 2000 (“bare earth” data obtained from the Atlas site).



Mount Airy 15 X 15 Minute Quadrangle, US Geological Survey, 1939



7.5 minute Quadrangle Maps for French Settlement (1991), Whitehall (1980), Killian (1980), Manchac (1979), Sorrento (1980), Mt Airy NW (1980), Mt Airy NE (1994), Ruddock (1979), Convent (1991), Lutcher 1994), Reserve (1994), and Laplace (1992), US Geological Survey.



Pontchatoula 30 X 60 Minute Geologic Quadrangle, Louisiana Geological Survey, 2003.



Interviews with Emile LeBlanc of LDW&F—who supervises the Wildlife Management Areas within the project area; Glen and Dale Martin—owners of Blind River Properties, which encompasses a large portion within the central and north areas; and Floyd Michel, Jr. and Jackie Robertson—who have extensive personal knowledge of the central and north areas as a result of living and guiding in the areas.

Using these sources, key project area topographic and bathymetric features were initially located and imported or digitized into a project GIS, including: •

Hydrologic features (primary and secondary natural and man-made channels, ditches, sloughs, oil-field canals, and lake boundary),

I:\Projects\LDNR\10001073-Maurepas Diversion\Reports-Working\V3 Topo & Bath Survey\Topographic and Bathymetric Survey Report.doc \9-AUG-07\BTR

2-1

SECTIONTWO

Review of Existing Data and Planning



Roads and pipeline and transmission line right-of-ways,



Spoil banks, levees and other embankments visible on aerial photography;

Planning for the topographic and bathymetric surveys took place over a series of meetings during the fall of 2003, subsequent to project initiation. Participants in the planning included the following project team members: •

Ken Teague and Patty Taylor, USEPA;



Chris Williams and Luke Lebas, LDNR;



Mike Patorno, Bob Jacobsen, Harry Harlan, Chris Reed, and Justin Roper, URS Corporation;



Randy Dixon, 3001, Inc.;



Gerald Menard, Evans-Graves Engineers, Inc.; and



Drs. Paul Kemp and Hassan Mashriqui, Louisiana State University, and Dr. Gary Shaffer, Southeastern Louisiana University (leaders of other ongoing research efforts in the Maurepas Swamp)

Field surveying was started in November 2003. Developed portions of the project area were largely accessible through the winter of 2003-2004, and channel cross section surveys of these areas were completed by March 2004. Areas north of US Highway 61 (Airline Highway) include the Maurepas Swamp and are extensively used through the winter months for deer hunting. Large tracts of the Swamp are privately held, and access is restricted during hunting season. Therefore, channel cross section survey work for the Swamp was not completed until April 2004. Spot surveying activities were largely completed by April 2004. (Spot surveys of elevations at project area camps were obtained in March 2005). All project surveys were tied to the system of project benchmarks (see Volume II, Secondary Benchmark GPS Static Survey, URS Corporation, April 2005). All elevations are in Feet NAVD-88, LDNR.

I:\Projects\LDNR\10001073-Maurepas Diversion\Reports-Working\V3 Topo & Bath Survey\Topographic and Bathymetric Survey Report.doc \9-AUG-07\BTR

2-2

SECTIONTHREE Section 3

THREE

Channel Cross Sections South of US Highway 61

Channel Cross Sections South of US Highway 61

The project area south of Airline Highway is largely developed and includes the residential and commercial districts within the towns of Garyville and Reserve, several large petrochemical and refining facilities, and sugar cane farms. The area drainage system consists of a network of man-made ditches and canals. The Hydraulic Feasibility Study Work Plan provides for the evaluation of potential backwater impacts from the proposed Diversion on the drainage system. [Note: Drainage is by gravity via the channel network through culverts across Airline Highway and into a set of larger canals that flow northward into the Swamp. During high Swamp water levels drainage is substantially reduced due to the very low gradient. The culvert draining into the Reserve Relief Canal is equipped with a gate that can be closed and a pump station is utilized to facilitate drainage during high Swamp water. St. John the Baptist Parish maintains a second pump station near the St. John Airport in Reserve.] To support evaluation of the developed area drainage system, project planning identified a total of 28 locations for obtaining cross sections. These locations were selected based on the need to supplement existing channel data, particularly with respect to the more significant canals and ditches. Figure 1 shows the cross section survey locations south of Airline Highway—which were designated as S-1 through S-28. The south area cross section surveys were performed by Evans-Graves using RTK GPS survey techniques. Appendix B provides the results of the surveys for these cross sections, which totaled 735 points. Based on the natural ground elevations determined outside the channels, the topography of the developed area ranges from elevations above 10 ft. along the highest portions of the old natural levee for the Mississippi River, to as low as 3 ft. at the northern margins of the agricultural land. Typical inverts of the drainage channels range from 5 to -1 ft. from south to north. These findings are consistent with the historic geologic and topographic data.

I:\Projects\LDNR\10001073-Maurepas Diversion\Reports-Working\V3 Topo & Bath Survey\Topographic and Bathymetric Survey Report.doc \9-AUG-07\BTR

3-1

SECTIONFOUR Section 4

FOUR

Channel Cross Section North of US 61/South of I-10

Channel Cross Section North of US 61/South of I-10

The portion of the project area between Airline Highway and I-10 is designated as the central area. The central area is largely undeveloped and mostly consists of swamp. One lobe of higher ground associated with an old Mississippi River crevasse extends a few thousand feet north of Airline Highway in the area of the St. John Airport. The central area drains to the north via two principal natural waterways (Blind River and Mississippi Bayou). Several man-made drainage canals (Hope Canal, Bougere Canal, East and West Marathon Canals, Godchaux Canal, and Reserve Relief Canal), oil-field canals, and smaller ditches (primarily in the southern reaches of the central area to facilitate drainage northward from Airline Highway) have altered the natural central area swamp flows. Historic swamp circulation patterns are also interrupted by the presence of I-10 and Louisiana Highway 641, as well as several minor dirt roads and a pipeline right-of way. Drainage ditches are present along most of the south side of I-10, along with culverts under the interstate which serve to equalize water levels on the north and south sides. Figure 2 shows the principal waterways in the central area. The proposed introduction of 1,500 cfs just north of I-10, and the modification of Hope Canal to serve as a diversion channel, may alter the circulation of flow in the central area. The Hydraulic Feasibility Study Work Plan provides for the two-dimensional modeling of flow patterns in the central area under baseline and various diversion scenarios. The Study is evaluating possible changes to water elevation and associated effects on gravity drainage from the south, as well as changes to detention times. To support evaluation of these flow patterns, project planning identified a total of 33 locations in the central area for obtaining cross sections. These locations were selected based on the need to supplement previous Pyburn and Odom channel surveys data (see Appendix A), particularly with respect to the more significant waterways. Figure 2 shows the cross section survey locations—which were designated as C-1 through C-33. The central area cross section surveys were performed by 3001, Inc. using a combination of RTK GPS and conventional survey techniques. Appendix C provides the data for the 445 points obtained on these cross sections. Table 1 provides a summary of the width, area, and invert for the central area channel cross sections.

I:\Projects\LDNR\10001073-Maurepas Diversion\Reports-Working\V3 Topo & Bath Survey\Topographic and Bathymetric Survey Report.doc \9-AUG-07\BTR

4-1

SECTIONFOUR

Channel Cross Section North of US 61/South of I-10

Table 1 Summary of Channel Geometry in Central and North Areas

Channel

Cross Section

AIRLINE CANAL ALLIGATOR BAYOU BAYOU BEC CROCHE BAYOU SECRET BAYOU SECRET BAYOU TENT BAYOU TENT BLIND RIVER BLIND RIVER BLIND RIVER BLIND RIVER BLIND RIVER BLIND RIVER BLIND RIVER BLIND RIVER BOUGERE BAYOU BOUGERE CANAL BOUGERE CANAL BOURGEOUS CANAL BOURGEOUS CANAL CANAL CANAL COCO BAYOU CROSS OVER CANAL DITCH DITCH DUTCH BAYOU DUTCH BAYOU DUTCH BAYOU EAST MARATHON CANAL GODCHAUX CANAL GODCHAUX CANAL HOPE CANAL HOPE CANAL

C25 N3 N20 N10 N9 N16 PO8 N2 N5 N7 PO10 PO14 PO15 PO16 PO17 N21 C20 C4 N12 N8 N17 N17B N25 C13 C1 C3 N18 PO4 PO9 C17 C14 C8 C2 C21

Channel Geometry (Reference el. -0.5) Width Ft

Area Sq. Ft.

Invert Ft. NAVD-88, LDNR

103.8 85.2 53.6 75.3 64.2 126.2 79.4 480.9 361.8 231.4 429.5 410.8 214.1 231.7 105.0 28.9 2.4 1.9 85.5 97.6 64.1 49.7 58.8 19.5 8.5 11.7 130.2 132.5 129.5 14.7 39.4 33.6 49.7 61.5

755.0 269.0 102.0 251.0 275.0 311.0 218.0 8710.0 9547.0 3125.0 9099.0 9776.0 2465.0 1450.0 990.0 22.0 0.3 0.3 354.0 406.0 207.0 160.0 19.0 6.9 3.2 1.6 633.0 1030.0 458.0 15.7 91.0 36.0 108.0 133.0

-11.3 -6.4 -3.9 -6.5 -8.5 -6.5 -5.0 -29.2 -51.5 -32.4 -37.0 -39.5 -19.0 -11.5 -15.5 -2.0 -0.8 -0.8 -7.4 -8.1 -5.8 -5.8 -1.0 -1.0 -1.0 -0.7 -10.8 -12.5 -7.0 -2.2 -5.1 -2.0 -4.0 -4.1

I:\Projects\LDNR\10001073-Maurepas Diversion\Reports-Working\V3 Topo & Bath Survey\Topographic and Bathymetric Survey Report.doc \9-AUG-07\BTR

4-2

SECTIONFOUR

Channel Cross Section North of US 61/South of I-10

Table 1 (Continued) Summary of Channel Geometry in Central and North Areas

Channel

Cross Section

HOPE CANAL HOPE CANAL HOPE CANAL HOPE CANAL MISSISSIPPI BAYOU MISSISSIPPI BAYOU MISSISSIPPI BAYOU MISSISSIPPI BAYOU MISSISSIPPI BAYOU MISSISSIPPI BAYOU NORTH OILFIELD CANAL NUMBER 12 CANAL RESERVE RELIEF CANAL RESERVE RELIEF CANAL RESERVE RELIEF CANAL RESERVE RELIEF CANAL RESERVE RELIEF CANAL SOUTH BAYOU SOUTH BAYOU SOUTH OILFIELD CANAL WEST BAYOU WEST INTERSTATE CANAL

N13 PO5 PO6 PO7 C30 N19 N24 PO11 PO12 PO13 PO2 N11 C10 C9 N27 PO1 PO3 N15 N15B N26 N14 N29

Channel Geometry (Reference el. -0.5) Width Ft 55.8 119.3 51.0 84.5 35.4 124.7 48.2 63.1 30.1 137.5 102.5 63.6 92.4 71.7 164.8 176.5 147.1 73.1 28.8 91.1 54.3 215.2

Area Sq. Ft. 137.0 362.0 135.0 384.0 41.0 512.0 95.0 196.0 24.0 423.0 510.0 167.0 231.0 160.0 873.0 1027.0 962.0 131.0 47.0 341.0 76.0 1405.0

Invert Ft. NAVD-88, LDNR -5.0 -5.0 -4.5 -7.5 -2.4 -8.0 -3.5 -5.3 -2.1 -5.0 -8.4 -6.3 -5.2 -4.6 -10.8 -10.3 -12.5 -3.2 -3.2 -7.6 -2.4 -11.0

I:\Projects\LDNR\10001073-Maurepas Diversion\Reports-Working\V3 Topo & Bath Survey\Topographic and Bathymetric Survey Report.doc \9-AUG-07\BTR

4-3

SECTIONFIVE Section 5

FIVE

Channel Cross Sections North of I-10

Channel Cross Sections North of I-10

The project area north of I-10 is designated as the north area and is comprised entirely of swamp. This area includes the lower Blind River, the western end of the Amite River Diversion Canal, and the southwest rim of Lake Maurepas. Other than camps located on the main channels there are no residents in the area. The north area drains into Lake Maurepas via several principal natural waterways (Blind River, Tent Bayou, Dutch Bayou, Bougere Bayou, Bayou Bec Crochet, and Mississippi Bayou) and man-made drainage canals (Hope Canal and Reserve Relief Canal). Drainage ditches are also present adjacent to most of the north side of I-10. In addition to the drainage channels, area hydrology is influenced by oil-field canals and transmission line rights-ofway. Figure 2 shows the principal waterways in the north area. The bulk of diversion water flow is expected to occur in the north area. The Hydraulic Feasibility Study will assess swamp water elevations under various diversion scenarios, velocities in sensitive channels, and the detention time of the diversion water in the swamp. To support evaluation of these flow patterns, project planning identified a total of 29 locations in the north area for obtaining cross sections. These locations were selected based on the need to supplement previous Pyburn and Odom channel data, particularly with respect to the more significant waterways. Figure 2 shows the cross section survey locations— which were designated as N-1 through N-29. The north area cross section surveys were performed by 3001, Inc. using a combination of RTK GPS and conventional survey techniques. Appendix D includes the results for the 532 points contained on these cross sections. Table 1 provides a summary of the width, area, and invert for the channel cross sections.

I:\Projects\LDNR\10001073-Maurepas Diversion\Reports-Working\V3 Topo & Bath Survey\Topographic and Bathymetric Survey Report.doc \9-AUG-07\BTR

5-1

SECTIONSIX Section 6

SIX

Crossing and Culvert Surveys

Crossing and Culvert Surveys

Surveys were performed by Evans-Graves using RTK techniques for various crossings and culverts in the south area and along I-10. In addition, URS used hand held GPS unit to obtain locations for several additional culverts along La 641 and Airline Highway. Appendix E provides the results for the 566 points include in these surveys. The typical invert for the I-10 culverts was between -0.5 and -1.0 ft.

I:\Projects\LDNR\10001073-Maurepas Diversion\Reports-Working\V3 Topo & Bath Survey\Topographic and Bathymetric Survey Report.doc \9-AUG-07\BTR

6-1

SECTIONSEVEN Section 7

SEVEN

Additional Channel Bathymetry

Additional Channel Bathymetry

Based on the review of existing data, particularly the interviews with the local landowners and guides, as well initial observations from project team members during reconnaissance visits to the areas, additional hydrographic features in the central and north areas were identified for further field investigation by URS. (These minor channels are shown on Figure 2.) URS personnel traversed these channels and obtained spot invert measurements at 47 locations. The invert data were taken with reference to the water surface and tied to nearby temporary benchmarks or staff gages. Appendix F provides the results of the URS spot surveys for additional channel bathymetry. The additional bathymetric data for minor channels and sloughs indicate that these features typically have an invert between -1.0 and -0.5 ft.

I:\Projects\LDNR\10001073-Maurepas Diversion\Reports-Working\V3 Topo & Bath Survey\Topographic and Bathymetric Survey Report.doc \9-AUG-07\BTR

7-1

SECTIONEIGHT Section 8

EIGHT

Additional Embankment Topography

Additional Embankment Topography

As a result of the initial reconnaissance, discussions with other project area researchers at Louisiana State University, and review of early hydrographic data, URS determined that higher resolution of channel bank topography would be needed to adequately characterize and model channel conveyance. URS therefore conducted a visual assessment of the banks for all of the identified channels. Banks were characterized as No Bank, Natural Bank, or Artificial Bank. Estimates were made of the typical controlling bank elevation—and the location, width, and invert of bank gaps—with reference to the water surface. Water surface elevations were established from nearby project temporary benchmarks or staff gages. Walking inspections and spot elevation measurements were also made for several embankment features: •

The natural Lake Maurepas bank;



The man-made railroad embankment which extends north from Hope Canal and turns westward terminating at Blind River;



Various segments of the man-made levees and roads which separate the agricultural development in the area of the St. John Airport from the swamp; and



Ground surrounding several project area hunting camps.

Appendix G provides the results for 153 URS spot embankment survey locations. The spot bank survey results showed that the major natural channels, particularly along the downstream reaches, are contained within a low natural bank, generally at an elevation of about +1.0 ft. The natural banks of Dutch Bayou are slightly higher, at +1.5 ft. Bank elevations of +2.0 ft. typically occur only at man-made spoil banks, embankments, or levees. Some ground elevations immediately adjacent to the camps surveyed ranged in the +2 to +3 range.

I:\Projects\LDNR\10001073-Maurepas Diversion\Reports-Working\V3 Topo & Bath Survey\Topographic and Bathymetric Survey Report.doc \9-AUG-07\BTR

8-1

SECTIONNINE Section 9

NINE

Swamp Topography

Swamp Topography

The original project plan envisioned performing several survey profiles within the Maurepas Swamp. However, data from the initial cross section surveys—together with information from interviewees and field surveys—indicated that there are no major features or trends in swamp topography that warranted surveying in support of the 2D hydrodynamic model. (Appendix H provides the results for 15 URS spot survey locations for swamp topography.) Furthermore, project area LIDAR data (see Figure 3) confirmed the location of known higher artificial banks within the swamp areas and did not indicate the presence of additional swamp topographic features. [Note: Figure 3 illustrates that the project area LIDAR data is composed of two sets of data—from March 1999 and March 2000 flights. There are clear discrepancies in the vertical control of the two sets of data.] The review of existing information on swamp topography supported a decision to concentrate the remaining field efforts on the additional channel and embankment surveys discussed above. Swamp vegetation is very dense and the swamp floor is heavily littered with detritus. Except for the dragline scars created from cypress lumbering in the early 20th century, point elevations tend to fall randomly within a narrow range. The cross sections and spot surveys indicated that swamp elevations typically range from 0.0 to 1.0 ft., with an average of about +0.5 ft. Elevations below 0.0 ft are seen in sloughs while elevations above +1.0 are common on the natural banks. This range is consistent with previous estimates by Dr. Kemp and Mashriqui that the average swamp elevation is about one-half foot below the average water elevation of Lake Maurepas (Development Plan for Diversion into the Maurepas Swamp, Louisiana State University, May 2004). The average water surface elevation in Lake Maurepas is about +1 ft. in NAVD88, LDNR. [Note: the LSU researchers have used a control network that yields an average water surface elevation of Lake Maurepas at about +1.5 NAVD-88 and an average swamp elevation of +1 ft.] Slightly higher swamp elevations are present around the lower end of Blind River and Alligator Bayou due to active deposition of Amite River Diversion Channel/Blind River fines in this area. Higher elevations are also seen toward the southern margins of the central area Swamp, as typified by the presence of oak and palmetto vegetation.

I:\Projects\LDNR\10001073-Maurepas Diversion\Reports-Working\V3 Topo & Bath Survey\Topographic and Bathymetric Survey Report.doc \9-AUG-07\BTR

9-1

SECTIONTEN Section 10

TEN

Data QC and High Resolution Digital Terrain Model

Data QC and High Resolution Digital Terrain Model

Topographic and bathymetric data for the central and north areas were used to prepare a high resolution digital terrain model (DTM). Development of the DTM has facilitated quality control (QC) reviews of project topographic and bathymetric data. Furthermore, the DTM has supported a detailed evaluation of the swamp geometry, hydrodynamics, and planning for the two-dimensional modeling effort. The DTM was developed in Land Development Desktop (LDD), a three-dimensional terrain modeling and editing program for use with AutoCAD (AutoDesk, Inc.) in the following steps: •

Survey data were checked for completeness, consistency, and reasonableness by URS engineers prior to importing the data into the GIS. Errors or discrepancies were resolved.



Feature locations (i.e., channel centerline, edge of water lines, channel banks, bank gaps, roads, levees, other embankments) were verified using GIS and the high resolution aerial imagery.



Features that were located visually in the field were geo-referenced (XY coordinates were assigned) using the high resolution aerial photography.



Feature GIS files and cross section data were exported to LDD (Appendix I includes copies of GIS files).



Using LDD 3D analytical tools, a complete series of vertices and edges were generated to represent the linear features, including grade transitions, feature intersections, and breaks (e.g. bank gaps).



2,467,060 vertices were produced in the final Linear Feature DTM, encompassing 175 miles of features (see Table 2).



A set of 130,000 interior point locations for the “interior” swamp were generated on 100 ft spacing and elevations between 0 and +1 ft NAVD-88, LDNR for these points were developed using a random number generator.



The DTM was then inspected in detail using 3D views on screen for consistency and reasonableness. This proved especially useful in editing channel intersections, checking grade transitions, and adjusting breaklines.



The combined DTM, with a total of nearly 2.6 million vertices, was then converted to a Triangulated Irregular Network (TIN) surface.

I:\Projects\LDNR\10001073-Maurepas Diversion\Reports-Working\V3 Topo & Bath Survey\Topographic and Bathymetric Survey Report.doc \9-AUG-07\BTR

10-1

SECTIONTEN •

Data QC and High Resolution Digital Terrain Model

Various outputs, including a detailed color contour map of the north and south area, were produced and reviewed.

The high resolution DTM has subsequently been used to generate a lower resolution DTM and TIN—with 175, 000 vertices—for the development of the 2D model finite element grid.

I:\Projects\LDNR\10001073-Maurepas Diversion\Reports-Working\V3 Topo & Bath Survey\Topographic and Bathymetric Survey Report.doc \9-AUG-07\BTR

10-2

SECTIONTEN

Data QC and High Resolution Digital Terrain Model Table 2 List of Significant Swamp Linear Features Feature

Length (miles)

Primary Channels and Associated Banks Reserve Relief Canal Blind River Mississippi Bayou Hope Canal Bayou Tent Dutch Bayou Subtotal

6.2 18.3 8.6 6.1 2.6 3.2 45.1

Secondary Channels and Associated Banks Mississippi Bayou, above Cross-Over Godchaux Canal Cross Over Canal West Interstate Canal South Oilfield Canal East Marathon Canal Alligator Bayou Bourgeous Canal SW-NE leg of Bourgeous Canal Number Twelve Canal West Bayou Bayou Secret Tennessee Williams Canal Airline Canal Tchackchou Bayou South Bayou North Oilfield Canal Subtotal

1.0 1.7 1.8 1.0 2.2 1.7 3.1 3.9 0.4 2.2 0.2 2.4 1.9 2.4 1.9 0.5 0.8 29.0

Sloughs and Associated Banks East-West between Reserve Relief MS Bayou Slough from Mississippi Bayou to South Oilfield Canal Branch Tenth Hard Time Canal Bougere Bayou Sawgrass Bayou N-S between Blind R and Alligator Bayou Peter's Run N-S trend, west of L Maurepas embankment NW-SE trend, between Dutch Bayou and L Maurepas embankment E-W trend, between Dutch Bayou and Mississippi Bayou N-S trend, between Blind R and Old RR embankment South of Old RR embankment

2.2 0.3 1.3 1.4 3.7 3.0 0.6 2.3 2.1 0.8 1.1 1.4 1.9

I:\Projects\LDNR\10001073-Maurepas Diversion\Reports-Working\V3 Topo & Bath Survey\Topographic and Bathymetric Survey Report.doc \9-AUG-07\BTR

10-3

SECTIONTEN

Data QC and High Resolution Digital Terrain Model Table 2 (Continued) List of Significant Swamp Linear Features Feature

SW-NE trend at west end of West Bayou 13 Mainline East-West Mainline Bougere Canal E_W east side of Hope Canal East-West Mainline Coco Bayou Lower South Bayou East of Reserve Relief Canal Between Mississippi Bayou and East Marathon Canal South of Old RR embankment West of Bayou Tent South of Bayou Secret Subtotal

Length (miles) 0.9 0.0 1.0 3.7 1.0 1.1 0.7 0.7 0.9 0.7 1.9 0.0 0.6 35.1

Ditches and Associated Banks Colonial Canal Northside of Airline Highway to Hope Canal I-10 northside I-10 southside Bougere Canal West of Bougere Canal West of Bougere Canal West Marathon Canal East of East Marathon Canal Subtotal

1.7 2.3 9.2 9.2 1.2 1.2 1.1 1.7 1.4 28.8

Total Channels

138.0

Additional Embankments Pipeline ROW Transmission Line ROW Old Railroad Embankment Lake Maurepas Natural Bank South Boundary Levee Hope Canal Road

10.7 9.3 4.5 4.4 5.6 2.6

Total Additional Embankments

37.2

I:\Projects\LDNR\10001073-Maurepas Diversion\Reports-Working\V3 Topo & Bath Survey\Topographic and Bathymetric Survey Report.doc \9-AUG-07\BTR

10-4

FIGURES

-

10 § ¨ ¦

Ca

na

/

l

0

S-20 S-13 ! ?

! ? S-1

! ? S-15

! ? S-12

! ? S-19

! ? S-14

Town or City

S-26

S-2

? !! ? ! ? S-27 ! ?

S-24

! ?

! ? S-17

! ? S-8

? ! ? S-21 ! S-5

! ? Garyville

637 S T

S-23

! ? S-9 Laplace

! ? S-6

6,000

LEGEND

S-25

! ? S-28

54 S T G:\Maurepas_DNR\Maurepas_Swamp_ProjectNo]\Deliverables\Maurepas_Figure1.mxd

£ ¤

! ? S-16

! ?

! ? S-18

4,500

1 Inch equals 3,000 Feet

S-22

61

3,000 Feet

n al

Mississippi Bayou

ne C a Pipeli

1,500

Reserve Relief Canal

pe

Godchaux Canal

Ho

! ? S-11

-

Secondaryn Benchmark

! ?

Cross-Section => S1 Interstate Highway

! ?

US Highway Louisiana Highway Railroad Hydrography Urban Area Parish

! ? S-10 53 S T

S-7

! ?

Lutcher--Gramercy

-

Reserve

PO29-SM-07

3179

S T

640 S T

! ? S-3 ! ? S-4 44

S T

Mississippi River

18 S T

18 S T

Edgard

640 S T 18 S T

Figure 1 Topographic and Bathymetric Survey Locations South of US Highway 61

Mississippi River Re-Introduction Into Maurepas Swamp (PO-29) Louisiana Department of Natural Resources US Environmental Protection Agency

( ! ? ! ( !

P&O 10

( ! ( ! ( ! ( ! ( !

nd Riv i er l B

( !

tte Bu

( !

n ea!( !( B r

l na!(!( a C!(

# *

N-3

( !

B All i g a to r

( !

( !

ou ay

# *

N-2

( !

1,500

3,000

4,500

6,000

Feet

( ! ( !

( !

( !

- PO29-SM-04

1 Inch equals 1,500 Feet

( !

( !

( !

( !

( !

0

/

( !

( ! ( !

# *

( !

# *

N-1

P&O 4

? !

( !

N-4

( !

( !

( !

# *

N-5

kment n a b m E d a o r Old Rail

( !

LEGEND

Peter's Run

( !

( !

( ! ( !

# *

N-18!(

( !

hB

P&O 18

( ! ( !

iv d

( ! ? ! ( !

# *

( !

N-6

? !

! ( ( !

P&O 9

( !

you

( !

Hope Canal

( !

( !

( !

is s

N-17 ( !

( ! ( !

# * ( !

( !

( ! ( !

( !

# *

-

N-19 ( !

is s

( !

# *

( !

M

( !

( !

Bayo u

T ent

ip p i Ba

( !

P&O 14

Lake Maurepas

( !

( !

( ! ? !

"

( !

( !

( !

( !

Du

( !

R

Bl

in

( !

tc

er

? !

a yo u

( !

# *

( !

- PO29-SM-05

( !

N-16 ( (! !

( !

( !

North Oilfield Canal

( !

( ! ( !

( ! ( !

( !

? !

( !

( !

Trans m ( !

( !

! ( ( !

ission

( ! ? !

P&O 15

( !

( ! ( ( ! !

( !

Line R

OW

ay

( !

(! ! (! ( ( ! ( !

( ! ! (

( !

( ! ( ! ( ! ! (

N-12

Transm

( ! ! ( ( ! ! ( ( !

No. 12 Canal

o y a B

( !

( !

( ! ! (

ission R

e B u

Cr o

c

OW

( !

( !

P&O 13

( !

# *

( !

( !

N-20

( !

( ! ( !

( !

ou

( !

Transm

( !

N-13

* !# (

( !

( !

( !

( !

( !

- PO29-SM-01

"

I-10

Tennessee - Williams Canal ( !

J Ba yo u D es

on e s

( !

( !

P&O 7

( !

- PO29-SM-02

" " " " " " " " " " " " " " " " "" " " " " " " " " """ " " " " " " " " " " " " " " " " " " " " " "" " " " " "" " " " " " " " " " " " " " " " " " " "" " "" " " " " " " " " " " " " " " " "" " "

( !

( !

"

" " " " " " "

( !

( !

N-22

" " " " " " " " "

( !

" " " " " " " "

( !

( !

inline

( ! ! (

# *

"

# *

# *

# *

( !

N-21

East - We s t Mainline ( !

( !

! ( ( !

Ca

"

( !

" " " "

" " " " " " "

( ( ! ! ( ( ! !

" " " " " " "

! ( ( !

N-28

P&O 11PO29-SM-03 ( C-30 !

C-27

" "" " " ? ! " " " " " "" " " " " " " " " " " " " " " " " " " " "" " " " " " " "" " " " "" " " " " " " " " " " " " " " " " " "" " " "" " " " " " " " " " " " " " "" " " " " " " " " " " " " "" " "" "

" " " " " " "

na

C-22

Pipeline ROW

l ( !

# *

( !

# *

C-23

"

( !

"

# *

l

Ai rli ne

C-19

# *

( !

Ca

# *

"

na

l

n Colo

ia

na l a C l

# *

C-20 (# ! *

( !! ?

"

# *

P&O 5 C-3 ( !

"

# * # *

"

"

"

"

"

"

"

( !

( !

( !

# *

N-29 ( ! ( !

( !

( !

( !

"

C-1

C-2

( !

t Sou

( !

# *

( !

"

ry und a o B h

"

"

"

C-4

"

C-11 ( !

( !

( ! ( !

RO e n i l e Pip

"

Pipe

# *

"

C-15

W # *

( !

! ( ( !

# *

C-5

( ( ! !

# * "

"

# *

C-32

"

P&O 12 ( !

( ! ! (

Cross-Over Canal ( ! ( !

( ! ( !

! ( ( !

C-17

"

# *

C-16

p

C-6

# *

( !

St. John Airport

! ( ( !

# *

C-12

South Boundary

US 61 - Airline Hwy "

Figure 2 Topographic and Bathymetric Survey Locations North of US Highway 61

( ! ! (

" "

!! ( (

! ( ( !

C-14

( !

# *

# *

"

C-13

(! ! (

( ! "

ry

C-10

! ( ( !

? !

W line RO

n da u o B h t Sou

( !

( !

( !

( !

! ( ( !

# *

( !

( !

! ( ( !

( !

# *

C-33

P&O 1

( !

( !

C-29

C-18

( !

"

"

( !

( ! ! ?

" "

OW R line e p i P

a Can ger e Bou

C-25

P&O 6

( !

Pipeline ROW

( !

( !

( !

( !

"

C-24

( !

"

( !

? !

# *

W es t I nt er s t at e C ana l

( ! ! (

"

Eas

# *

# *C-31 # *

"! (

( (! !

"

:\Maurepas_DNR\Maurepas_Swamp_ProjectNo]\Deliverables\Maurepas_Figure2.mxd

( !

I-10

# " " C-28 * "

C-21

pe

( !

( !

( (! !

( !

"

# *

( !

( !

( !

"

( c! ( !

( !

(! ! (

Ho

( !

( !

Wes

c ha uT

ko u

( ( ! ! ( !

( !

( !

ROAD

( !

W e RO n i l e l Pip Shel

P&O 17

o

Bay

? !

! ( ( !

ROW

( !

l ana C n atho r a tM

( !

Highly Broken Bank

( !

( !

# *

Artificial Bank

( !

# "! ( * "

"

# *!(

N-24

Hard-Time Canal

# *

( !

13 Ma

La Hwy 641

Ba

y o u C adet ( !

C-26

N-27

( !

( !

( !

"

"

( !

( !

( !

( !

? !

" " " " " "

( !

( !

( !

( !

" " " " " "

( !

( !

OW

Godchaux Canal

( !

" " " " " " "

( !

( !

South Oilfield Canal #* N-26

N-23

anal C n o ath t Mar

( !

" " " " " "

# *

Bou ge

( !

( !

( !

( !

( !

Mis

P&O 16

( !

# *

( !

( !

( !

Branch Tenth

Primary

Natural Bank

( !

( !

u

? !

( !

( !

Bayou Secret

N-10

ission R

yo a B i p p i siss

# *!(

N-9

( !

! ( ( !

( !

ayou

( !

( !

re B

Hope Canal

( !

HYDROGRAPHY

EMBANKMENT

( !

( !

( !

( !

? ! ! (( !

( !

Secondary Benchmark

Interior Ditch

( ( ! !

( !

# *

# *

N-25

URS Cross-Section

Ditch

! ( ( ! ! (

( ( ! !

( !

( !

you a B co # *

( !

N-11

Co

P&O 3

( !

( ! ( !

( ( ! ! ? ! ( ! ( !

Reserve Relief Canal

( !

( !

( !

( !

( !

( ! ( !

( ! ( !

# *

N-15

P&O Cross-Section

Slough

( !

Reserve Relief Canal

( !

( ! ! (

P&O 8

et

( !

# *

! ( ( !

? !

( !

( !

ay

( !

N-8

( !

B

( !

( !

( !

Mississip pi B

( !

( !

# *

N-14

( !

P&O 2

ch

Bo

( !

urgeois Canal

st We ou y Ba !(

( !

So u th

# *

N-7

ou

( !

CULVERT

Secondary

( ! (! ! (

GAP

# *

C-8

"

"

C-7

"

"

"

C-9

Mississippi River Re-Introduction Into Maurepas Swamp (PO-29) Louisiana Department of Natural Resources US Environmental Protection Agency

/ 0

1,500

3,000

4,500

6,000

Feet

1 Inch equals 2,000 Feet

Legend Flight Line March 1999

iv e

r

Flight Line March 2000

dR

>-1

Bli n

-1 to 0.5 -0.5 to 0 0 to 0.5 0.5 to 1

Lake Maurepas

1 to 1.5 1.5 to 2 2 to 2.5 2.5 to 3 3 to 4 4 to 6

Hope Canal

Reserve Relief Canal

6+

La Hwy 641

I-10

Figure 3 LIDAR Data North of US Highway 61 Mississippi River Re-Introduction Into Maurepas Swamp (PO-29) Louisiana Department of Natural Resources US Environmental Protection Agency

APPENDIX A PYBURN AND ODOM PROJECT AREA CROSS SECTION DATA

APPENDIX B CHANNEL CROSS SECTIONS SOUTH OF US HIGHWAY 61

APPENDIX C CHANNEL CROSS SECTIONS NORTH OF US HIGHWAY 61

APPENDIX D CHANNEL CROSS SECTIONS NORTH OF INTERSTATE 10

APPENDIX E CROSSINGS AND CULVERTS SURVEYS

APPENDIX F ADDITIONAL CHANNEL BATHYMETRY

APPENDIX G ADDITIONAL EMBANKMENT TOPOGRAPHY

APPENDIX H ADDITIONAL SWAMP TOPOGRAPHY

APPENDIX I CD COPY OF REPORT INCLUDING APPENDICES AND ADDITIONAL GIS DATA FILES Additional GIS Data Files include: •

Channel Centerlines



Embankments, including natural channel banks, artificial banks (which includes channel spoil banks, railroad embankment, and levees)and rights-ofways



Roads

Vol_III_Topographic and Bathymetric Survey Report-FINAL.pdf ...

Vol_III_Topographic and Bathymetric Survey Report-FINAL.pdf. Vol_III_Topographic and Bathymetric Survey Report-FINAL.pdf. Open. Extract. Open with.

26MB Sizes 0 Downloads 174 Views

Recommend Documents

Geographic and bathymetric distribution of ...
Pan-American Journal of Aquatic Sciences (2007) 2 (3): 255-260 ..... latitude one-degree bins (a regression for each line is shown) ... Marine fronts at.

Home and Garden Survey - PDFKUL.COM
Furniture and Home Appliances. 92%. 8%. Yes. No. N=340. Do you ever use a search engine (such as Google, Yahoo, AOL, MSN or Ask Jeeves) when you research or purchase Home Furnishings, Appliances, or Improvement items online? Source: 2005 Home and Gar

Home and Garden Survey
Best Buy. Lowe's Home Improvement. Home Depot. Wal-Mart. Target. N=130. You indicated you use a search ... Over the phone. N=292. After using a search ...

CAPI Survey Questionnaire - China Household Finance Survey
Part 1: Demographic Characteristics . ...... Was the degree acquired abroad? ... Last year, did 【 CAPI LOAD NAME 】 live in this ..... Can Choose Multiple)【Card A11】. 1. Politics. 2. Economics. 3. Society. 4. Science. 5. .... computer serv

CATI Survey Questionnaire - China Household Finance Survey
situation of losing jobs and then being reemployed? 1. Yes. 2. No[skip to .... computer and other durables? F04a. Last quarter, how ... Best regards for you! Bye!

CATI Survey Questionnaire - China Household Finance Survey
A01b. [CATI load name] contact information [correct the phone number and dial it]. A02. .... Last quarter, what was the total net business income of your family?

SURVEY AND LAND RECORDS-2016august@PSC WINNERS.pdf
Page 1. Whoops! There was a problem loading more pages. Retrying... SURVEYOR GR - II - SURVEY AND LAND RECORDS-2016august@PSC WINNERS.pdf.

Survey - College of William and Mary
Feb 1, 2013 - Policy Indicators Department in the Technical Secretariat of the Presidency ... the Center for Global Development, the London School of ..... reports that the MCC submits to the U.S. Congress each year to ... One of the central goals of

Nigeria Demographic and Health Survey (NDHS) Infographics.pdf ...
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. Nigeria ...

Nigeria Demographic and Health Survey (NDHS) Factsheet.pdf ...
Nigeria Demographic and Health Survey (NDHS) Factsheet.pdf. Nigeria Demographic and Health Survey (NDHS) Factsheet.pdf. Open. Extract. Open with.

Survey - College of William and Mary
Feb 1, 2013 - with a small number of survey recipients (Bhutan, India, and Laos), countries that were Candidates for only a few years .... standards as an important catalyst for business climate reform (World Bank 2007).xxii ...... four, accounting f

Games-And-Decisions-Introduction-And-Critical-Survey-Dover ...
Games And Decisions: Introduction And Critical Survey (Dover Books On Mathematics) PDF eBook. MODELS AND ULTRAPRODUCTS: AN INTRODUCTION ...

National Hispanic Survey Results
Jun 21, 2013 - Among all Hispanics, six in ten, 60%, support granting legal status to those .... California. 27. 26. 21. 25 ... Not College Graduate. 27. 28. 15. 28.

Survey: 2015 Elections (PDF)
Dec 18, 2014 - The Secretary of State's office is requesting a list of scheduled elections your county will be conducting in 2015. Please complete and return the ...

Survey: 2015 Elections
Dec 18, 2014 - The Secretary of State's office is requesting a list of scheduled elections ... via fax to (916) 653-3214 or e-mail to [email protected], ...

2013 Benchmark Survey - Rackcdn.com
... More About Buyers. About The Survey Sample. About Demand Gen Report. 3. 7. 8. 9. 10. 11. 11 ... those dollars on social media as well as developing white papers ... efforts will get top priority, according to the respondents to the 2013 ... Marke

Survey of abuse and violence by patients and relatives towards ...
E-mail: [email protected]. Accepted: 21 ...... E-mail address: [email protected] ...... batch imprecision ranged from

Survey of abuse and violence by patients and relatives towards ...
1 University Department of Anaesthesia, Gartnavel General Hospital, 30 Shelley ... used during structured interviews [13], or computer ..... years [9], few studies have tested the content or criterion ..... We also thank Heini Huhtala, Master of Scie

IAASE: Growth Model Survey This survey was ...
It increases teacher motivation to try new things and measure the results of ... Professional development should be included as well to offer support to teachers. .... Factories control the quality of the end product by mandating the quality of the.

Waste Watch Survey Residential Survey Results (Final Summary ...
Waste Watch Survey Residential Survey Results (Final Summary).pdf. Waste Watch Survey Residential Survey Results (Final Summary).pdf. Open. Extract.

survey report.pdf
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. survey report.pdf.Missing:

Volunteer survey
Thank you for encouraging your student's participation in the arts. Your assistance is greatly appreciated and can range from providing refreshments, to painting, to assisting with costumes, props, etc. Many people find it very rewarding to be involv

UK Automotive Survey
Are you involved in any of the following functions for your company? Select all that apply. Source: 2005 Logistics Survey, conducted by Media-Screen and GMI ...