Health and Safety Management Systems Punjab State Power Corporation Limited
Site Audit Observations
1) GNDTP – Bathinda; Date of Audit: 17.03.2015 a) Admin Building i)
Fire exit boards not evidenced.
b) Stage-2 i)
Fire extinguishers are not kept in proper place. Those should place, so convenient to use during any emergency.
ii)
Fire extinguishers are not sufficient, if any fire happen.
iii) No display boards for fire extinguishers. iv) No sufficient rubber mats at electrical panels / switch boards. v) Switches (#4) board very ne to door. Remove or kept place another convenient place. c) First Aid i)
No patient register evidenced. (Register should include columns like Date, Name of patient, Problem noticed, Medicines used, Remarks, etc….)
ii)
No separate dust bins for medical waste, plastic waste. (Use standard bins)
iii) No evidenced of using syringe burner. iv) No evidence of First aid boxes available at all major locations in the plant. d) DMP i)
MSDS not available for Aluminum Sulphate.
ii)
No proper identification for location of Fire Extinguishers.
iii) Hazards Identified – On ground Floor, Stairs, Pipes, Trenches (no covers), Surface uneven. iv) Wooden boxes kept at entrance. v) Drainage is open condition. Should be closed. vi) Vision statements observed two. One is for PSPCL and second is for GNDTP. Need review. e) Canteen i)
Coal using for cooking – back side on canteen. Need review.
ii)
No exact fan available in store.
iii) No proper cleaning. Rats evidenced in the canteen. iv) No complaint book evidenced. f)
Transformer i)
No fencing for transformer.
ii)
Leakage from cold tunnel.
g) Switch Yard
Signature of Auditor:
PSPCL-OHSAS 18001
Page No: 1 of 3
Health and Safety Management Systems Punjab State Power Corporation Limited
Site Audit Observations
i)
Door for switch yard found open. It should be locked.
ii)
Water found in switch yard area.
h) Plant i)
First aid boxes not evidenced inside the plant.
ii)
Type of fire extinguisher not mentioned on fire extinguishers (Fire point no. 2D to 2B)
iii) No cover for electrical cables – turbine side. i)
Safety Officer i)
Emergency assembly points not evidenced in the Plant lay-out.
ii)
No evidence of smoke detectors tested periodically.
iii) No observations recorded during mock-drill. 2) GHTP – Lehra Mohabhat; Date of Audit: 19.03.2015 a) Plant i)
No display of speed limits for vehicles.
b) Environmental Lab i)
No provision for exhaust of air (no fan)
ii)
No proper support to stairs. Gap (hazard) observed.
iii) No rubber mats for electrical panels / switch boards. iv) No lock for water cooler. c) Electrical / Mechanical work-shop i)
Garbage observed in front of main entrance.
d) Fire station i)
Fire sand buckets observed in wet condition - 2 nos.
ii)
Drainage observed in open condition and water flowing.
e)
f)
Ash Plant i)
Old registers kept in control room.
ii)
No evidence of noise level monitoring
T.G i)
No pipes for Water Hydrants, FHB-71
ii)
No proper / easy access to Fire Extinguishers
iii) Only cotton available in the First-Aid box. iv) No proper support to Stair. g) Hydrogen Plant i)
Place provided to Fire Extinguishers is so congested.
ii)
No rubber mats for Electrical Panels.
Signature of Auditor:
PSPCL-OHSAS 18001
Page No: 2 of 3
Health and Safety Management Systems Punjab State Power Corporation Limited
Site Audit Observations
iii) House-keeping not good. iv) No evidence of Hydrogen Cylinders is tied with chain. h) Coal plant i)
No aisle marking evidenced. (marking of walkways) – need review.
ii)
Electrical trenches are open.
iii) Water hose pipe(s) kept on ground (open place); properly not handled. i)
j)
Canteen i)
House-keeping can be improved.
ii)
No evidence of complaint book available.
Dispensary i)
No standard bins used for collection of medical waste.
3) GGSSTP – Roopnagar; Date of Audit: 21.03.2015 a) Coal testing lab i)
Drainage observed in open condition
ii)
Fire extinguishers – Have only check-up date. No due date or frequency.
b) Turbine 5, unit 6, unit 3, switch gear – no rubber mats for electrical panels and control panels. c) No identification boards for fire extinguishers. d) First Aid box – no list available for the medicines to keep. e) Aisle marking for all areas can be improved. f)
Sub-station 220 – Grass and water seepage evidenced.
Page 1 of 3. Punjab State Power. Corporation Limited. Health and Safety Management Systems. Site Audit Observations. Signature of Auditor: PSPCL-OHSAS ...
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. site visit & field inspection.pdf. site visit & field inspection.pdf. Open. Extract. Open with. Sign In. Mai
Organisation of Committee Site Visits. Page 3 of 5. Planning Committee Site Visit Protocol final April 2013.pdf. Planning Committee Site Visit Protocol final April ...
As such, the result-oriented company's key performance ... when compared to site average (Source: Google Analytics data, 2012-2013). According to the SEM ...
PT Barnum - The Art of Money Getting. SEO Elite. Getting your website ranked high on the Search Engines can sometimes seem almost impossible. Until now.
Mr. Micawber, one of those happy creations of the genial Dickens, puts the case in a ...... SEO Elite is the Daddy of all SEO software, helping you to get a.
3: College of Computing, Georgia Institute of Technology, USA .... Systems Bioinformatics CSB2007, 13-17 August 2007, University of California, San Diego.
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. Visit of Prize.pdf.
r - ;, ,....r . ,.... ., ·- is a popular site that occupies almost 900 acres in. Mahomet, along the corridor of the Sangamon. River. Lake of the Woods holds many special.
Jan 9, 2018 - Knuckles, producing different grades like SG iron (all grades), Grey iron and high alloy iron (SIMO, GJV. SIMO). The main customers are ZF-TRW (Europe) , THK Rhythm , Volvo , Bosch , Turbo Energy Limited ,. Bosch Mahle Turbo Systems , T
Mathematical Problem Solving. (Stephan Wagner and. Dimbinaina Ralaivaosaona,. Stellenbosch University). The August and January intake also completed ...
... ft2, respectively. Find the. probability of visiting the gift shop by the. customers. Which mall would be preferred and. why ? 10. MFR-019 1 P.T.O.. Page 1 of 2 ...
processing does not necessarily include testing of all parameters. ..... Supply current. (two amplifiers). VCC = MAX, VO = 0.5 V,. No load. Full range. 1 ...... TI warrants performance of its hardware products to the specifications applicable at the
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. site axon.pdf.
There was a problem previewing this document. Retrying... Download. Connect more apps... Try one of the apps below to open or edit this item. Site Inspections.
4th IASPEI / IAEE International Symposium: Effects of Surface Geology on Seismic Motion. August 23â26, 2011 · University of California Santa Barbara. Complex Site Response: Does One-Dimensional Site Response Work? Laurie G. Baise. Eric M. Thompson
Gave the lustre of mid-day to objects below,. When, what to my wondering eyes should appear,. But a miniature sleigh, and eight tiny reindeer,. With a little old ...
afternoon and take rest under a Neem tree. Baba dug a pit, 2 feet deep, under the Neem tree and kept a Deep lit in that pit. One octangular. Deepgriha called Nanda Deep has been built in marble stone in memory of this place. It constantly burns in a
and 5pm on Thursdays for Messy Art Club, Mad Scientists Club, or Lego. Club. More Reading Programs. Ask us about summer reading programs, winter reading (Paws to Read). and 500 Books Before Middle School for elementary age students. Did you know... L