DEVELOPMENT OF A GROUND SOURCE HEAT PUMP SYSTEM WITH GROUND HEAT EXCHANGER UTILIZING THE CAST-IN-PLACE CONCRETE PILE FOUNDATIONS OF BUILDINGS

K. Sekine Technology Center, Taisei Corporation 344-1, Nase-cho, Totsuka-ku, Yokohama 245-0051, Japan Tel: 81-45-814-7239 [email protected] R. Ooka, S. Hwang, Y. Nam Institute of Industrial Science, University of Tokyo 4-6-1 Komaba, Meguro-ku, Tokyo, Japan Y. Shiba Development, Zeneral Heatpump Industry Co., Ltd, M. Eng. 121, Mishinden Ohdaka-cyo, Midori-ku, Nagoya 459-8001, Japan

1.

BACKGROUND

Ground-source heat pump (GSHP) systems can achieve a higher coefficient of performance than conventional airsource heat pump (ASHP) systems because the ground, which functions as the heat source or sink, is at a higher temperature in winter and lower in summer than the air temperature (Kavanaugh 1992; Kavanaugh et al 1997). In addition, there will likely be some mitigation against the effects of the heat island phenomena, as this system does not emit exhaust heat into the atmosphere during air conditioning. However, GSHP systems are not popular except as experimental versions in Japan. This is primarily due to the high cost of boring to run piping underground. For example, such boring costs average about ¥3,000/m (approx. US$30/m) in the USA, whereas the same work is about ¥10,000/m (US$100/m) in Japan. Thus, even if the heat pump performance in GSHP systems is more effective than that of the more common ASHP systems, the GSHP systems are unable to recoup the initial piping costs within their lifecycles. Recently, GSHP system employs the foundation piles of buildings as heat exchanger (so called “energy pile system”) is introduced into some buildings in order to reduce the initial boring cost (Hamada et al 1997; Arup Geotechnics 2002; Presetschnik et al 2005). However the effective and low cost design method for energy pile systems has not been developed yet. In addition, almost energy pile systems have used the precast prestressed concrete pile or the steel pipe pile. Recently, in Japan, the foundation piles of buildings in the urban area have used the cast-in-place concrete pile foundation for the reason of the traffic circumstances when carrying of piles or the cost reduction. The authors have developed a GSHP system (energy pile system) that employs the cast-in-place concrete pile foundation of buildings. In this research, a full-scale experiment was conducted. The heat exchange capability of this system, the subterranean temperature changes and performance of the heat pump were investigated. Furthermore, the construction costs of this system were also examined.

2.

SYSTEM OUTLINE

In this system, some U-tubes are arranged around the surface of cast-in-place concrete pile foundations as shown in Figure 1. The U-tubes are normally made of high-grade polyethylene or cross linked polyethylene. U-tube employed in this system is made of polyethylene. Polyethylene is very steady chemically, and is strong also in the temperature change. Thus, there is no worry to which polyethylene is deteriorated even if concrete curing (heating, swelling/shrinking) occurs. These U-tubes are usually 3/4 or 1 inch (27 or 34 mm) in diameter. The usual diameters of cast-in-place concrete pile foundations are from 1500 to 4000 mm. Thus, this arrangement is expected to offer superior heat exchange performance. The U-tubes are installed against the reinforcing bars used in the cast-in-place concrete pile foundations, so the strength of the foundation pile is ensured. Air conditioning

Cast-in-place concrete pile φ1500~4000mm

Geothermal Heat Pump

U-bend φ20~25mm Foundation piles

Figure 1:Outline of the heat exchange system using cast-in-place concrete piles

In the case of application of 1500mm cast in place concrete pile to the usual office building in Japan, one pile is usually set per 30 to 40m2 floor area each. In this study, heat extraction/rejection rate per one pile was about 180W/m. Therefore if pile length is 30m (it is very general in Japan), heat extraction/rejection rate per one pile became 5.4kW. This ability corresponds to the air conditioning load for 2 to 3 floor areas, i.e. about 1/3 of the total air conditioning load of a 8 stories office building which is very popular in Japan. Heat source for air conditioning in the office building is usually divided into several parts. In this case, geothermal heat from this pile system can be used as one parts of heat source. The other air conditioning load is supplemented with the usual air-source heat pump. These methods are quite reasonable and applicable. In this paper, a basic performance and the construction cost of this system are examined.

3.

FULL-SCALE EXPERIMENT

3.1 Experimental Equipment Outline An experimental institution was built on-site at the University of Tokyo in Chiba. Chiba is east of Tokyo, and the average annual air temperature is about 15.4°C, with the average air temperature in August being about 26.4°C and in January about 5.4°C. Accordingly, both heating and cooling functions are necessary. A plan of the experimental institution and the system configuration is shown in Figs. 2-3. The results of this experiment were obtained at a local site. Thus, people should apply these results at other sites carefully. A borehole log at this site is also shown in Fig.2 in order to show the locality of this experiment.

4537.5

3600

4537.5 depth [m] 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20

Fun coil unit

Experiment room A

Geothrmal heat pump & Control panel

N 4000

×:Underground temperature measurement point

3675

Radiation panel

Preparation room

Experiment room A

Foundation pile B

Foundation pile A 45°

22.5° U-bends

1500

1250

3250

1500

1250

story [m]

log

soil

1.7

loam

3.2

clay loam

0.7 1.3 0.8

tuff clay silty clay clay fine

color

dark brown | pale red brown

groundwater level

12.67

fine sand

pale dark brown

soil map

6000

Figure 2:Plan of the Experimental Institution and Sail Map

FM

FM



Geothermal heat pump

T



Expansion tank 50 L

Experiment room B Radiation panel RC2000 P50 39line 1,940 L/h Cooling 3,000 kcal/h Heating 3,800 kcal/h

FM

Expansion tank 50 L

Radiation Panel

T

Wh

Watt-hour m eter

FM

Fun coil unit

Experiment room A Fun coil unit Cooling 3,000 kcal/h Heating 3,800 kcal/h

Wh Wh

Watt-hour m eter

Cold and Hot water pump flow:33L/min, head:12m, electric motor output:0.25kW Heat souce water pump flow:33L/min, head:25m, electric motor output:0.75kW

SH RH

SH RH

SH RH

20000 57.4

Watt-hour m eter

Geothermal heat pump Cooling:4.6kW (Cold water:12/ 7°C, Cooling water:30/35°C) Heating:5.7kW (Hot water:40/45°C, Heat souce water:14/ 9°C) Electric consumption:1.6kW (Cooling), 1.8kW (Heating) 200V Refrigerant : R407C

U-bends Polyethylene tube 25A, 20m

Cast-in-place concrete pile diameter:1500mm, (20m) U-bends 8 per pile

Figure 3:System configuration

There were two cast-in-place concrete piles (both 1,500 mm in diameter, 20 m tall) around which 8 U-tubes (External diameter: 34.0 mm; internal diameter: 28.8 mm) were installed. It is possible to control the number of Utubes in operation by opening and closing their valves. The system employed in this experimental equipment consists of a water-to-water heat pump with a reciprocating compressor (4.6 kW cooling, 5.7 kW heating). Cold and hot water circulates through a fan coil unit and a radiation panel in two examination rooms respectively, as shown in Figure 2. The flow of cold and hot water is 27 l/min (0.00045 m3/s). The flow of the heat source (sink) water is 33 l/min (0.00055 m3/s).

This system has two rooms. One has a fan coil unit installed. The other has a radiation air conditioner. Thermostat and electrical valves control the amount of water supplied to the fan coil unit. 3.2 Experiment Outline The heat pump in this system was operated from 9:00 to 18:00, Monday to Friday as in typical office buildings. It was not operated on Saturday or Sunday. In summer (from June to September), heat was discharged (sunk) into the ground. Conversely, in winter (from December to March), heat was extracted (sourced) from the ground. A list of the measurement items is shown in Table 1. Table 1:The Measurement Items Measured Item

Measuring equipment (permissible range)

Measurement point

Subterranean temperature

T-type thermo couples (±1°C)

Depth: 1m, 10m, 19m

U-bend surface temperature

T-type thermo couples (±1°C)

Depth: 1m, 10m, 19m

Heat source/sink water temperature

Platinum measurement resistor (±0.5°C)

In the pipe

Cold and hot water temperature

Platinum measurement resistor (±0.5°C)

In the pipe

Water flow

Flow meter (±2%)

In the pipe

Electrical power used

Electric power meter

Power panel

Outside temperature, relative humidity, wind velocity, wind direction, quantity of solar radiation, rainfall

4.

COOLING AND HEATING RESULTS IN 2003

4.1 Underground Temperature Figure 4 shows the variations in the underground temperature at measuring points A and B and air temperature in 2003. The subterranean temperature was about 20°C one meter below ground level (G.L. –1m), about 19°C at G.L. –10m and about 17°C at G.L. –19m in both measuring points A and B as shown in Fig. 6 at the start of the airconditioning operation (7/16). The subterranean temperature at each point gradually rose thereafter. The subterranean temperature at G.L. –1m had reached about 25°C by the time the air-conditioning operation ended. The subterranean temperature at G.L. –1m was significantly influenced by the ambient air temperature. However, subterranean temperatures only changed a few degrees at G.L. –10m and G.L. –19m throughout the year. At the start of the heating operation (12/25), the subterranean temperature at G.L. –10m was about 19°C, while that at G.L. –19m was about 17°C. The subterranean temperatures at each point fell gradually after the start of this operation. The subterranean temperatures at G.L. –10m and G.L. –19m stabilized at about 15°C during the heating operation in February and remained nearly constant until the operation ended (3/28). 30

30 10

25

Measure Point A 45°

20

Heating

GL -1m GL -10m

5

5

2750

Foundation Pile A

GL -19m

Foundation Pile A

15

Temperature [ºC]

25 20 15

GL -1m GL -10m

GL -19m Air-Temperature

1250

0

0

Temperature [ºC]

45°

Heating

10

Cooling

Measure Point B

Cooling

6/28

8/17

10/6

11/25

1/14

3/4

4/23

6/28

8/17

10/6

11/25

1/14

3/4

4/23

Figure 4:Underground and air temperature variations (left: point A, right: point B)

30 25 15

20

:Temperature(13:00) :Heat Source Water Temperature

0

10

5

10

Temperature[ºC]

40 35 30 25 20

:Temperature(13:00) :Heat Sink Water Temperature

15

Temperature[ºC]

4.2 Heat Source/Sink Water Temperature The air temperature and heat source/sink water temperatures for cooling and heating are shown in Figure 5. The heat sink water temperature at the start of the cooling operation was about 20°C, rose gradually after that and reached about 29°C just before the end of the cooling period. The average temperature of the heat sink water and air during the cooling period were about 24.5°C and 29.2°C respectively. The heat sink water temperature was about 4.7℃ lower than the air temperature on average for the cooling period. And the maximum difference between the water temperature and the air temperature was 12.3℃ for the cooling period.

6/28

7/18

8/7

8/27

9/16

10/6

12/5

12/25

1/14

2/3

2/23

3/14

4/3

4/23

Figure 5: Heat sink/source water temperatures (left: cooling (sink), right: heating (source)) On the other hand, the heat source water temperature at the beginning of heating was about 17°C and fell gradually after the start of the operation and remained at about 13°C from early January until the end of March. The average air temperature during the heating period was about 9.9°C, while the minimum was about 1.1°C. the heat source water was about 3.1℃ higher than the air temperature on average for the heating period. The maximum difference between the water temperature and the air temperature was 11.9℃ for that period. Thus, using the ground water as a heat source or sink was more effective than using ambient air. Accordingly, GSHP is expected to be more effective than ASHP both in terms of cooling and heating.

4.3 Heat Extraction/Rejection From/Into The Ground The averages for the heat extraction and rejection either from or into the ground of the foundation piles A and B at the outset of the cooling and heating periods is shown in Figure 6. The maximum values for heat rejection were 158 W/m (pile A) and 164 W/m (pile B) respectively, while the average values for heat rejection were 100 W/m (pile A) and 120 W/m (pile B) respectively while cooling. The heat rejection per paired U-tube was about 12.5~15 W/m during the cooling period. Pile B seems to have higher heat rejection than Pile. It is supposed that there are some reasons. For example, the local soil thermal properties around pile A and B are different, mass flows in U-tube around pile A and B are different due to the difference of pipe friction etc.

7/8

7/18

7/28

8/7

8/17

8/27

9/6

9/16

9/26

10/6

20

200

10 0 -10 -20

Average of Air-Temperature[°C]

150 100

:Pile A :Pile B

50

Heat Extraction from The Ground[W/m]

Average of Air-Temperature

0

30 20 10 0 -10

:Pile B

Average of Air-Temperature[°C]

200 150 100 50

:Pile A 0

Heat Rejection into The Ground [W/m]

Average of Air-Temperature

12/5

12/25

1/14

2/3

2/23

3/14

4/3

4/23

Figure 6:Heat extraction/rejection from/into the ground (left: cooling (sink), right: heating (source))

The maximum values for heat extraction were 119 W/m (pile A) and 124 W/m (pile B) respectively, while the average values were 44 W/m (pile A) and 52 W/m (pile B) respectively while heating. Heat extraction per paired Utube was about 6~7 W/m during the heating period.

4.4 Coefficient of Performance The coefficient of performance (COP) for this system, the heat sink/source water temperature and air-conditioning load while cooling and heating are shown in Figures 7. The maximum COP was 6.4, while the average was 3.7 while cooling. When the air-conditioning load was high or the heat sink water temperature was low in August, the COP recorded high values. The maximum COP was 5.0 while the average was 3.2 while heating. When the airconditioning load was high or the heat source water temperature was high in January, the COP recorded high values.

6.0

6.0

5.0

5.0

2.0

3.0

COP

4.0

4.0 3.0 2.0

:July :Augast :September

0.0

0.0

1.0

COP

1.0

:July :Augast :September

15

20

25

30

35

0.0

4.0

6.0

8.0

5.0

:December :January :February :March

0.0

0.0

1.0

1.0

2.0

3.0

3.0

COP

4.0

4.0

5.0

:December :January :February :March

2.0

COP

2.0

Load of Air-Conditioning[kW] 6.0

6.0

Heat Source Water Temperature[゜C]

10

12

14

16

18

Heat Sink Water Temperature[°C]

20

0.0

2.0

4.0

6.0

8.0

Load of Air-Conditioning[kW]

Figure 7: Coefficient of performance (top: cooling, bottom: heating)

Although, the authors had expected that the average heat extraction/rejection values would reach 160 W/m per pile (i.e. 20 W/m per U-tube), the actual value was much less than expected. It is thought that this was due to the low air-conditioning load on this system; therefore an additional load was installed, and the cooling experiment was repeated in 2004. These results will be described in next section.

5.

COOLING RESULTS IN 2004

The cooling results in 2004 are shown in Figures 8~10. The maximum values for heat rejection were 259 W/m (pile A) and 278 W/m (pile B) respectively, while the average values were 204 W/m (pile A) and 220 W/m (pile B) respectively from 6/16 to 8/21. The average values for heat rejection were 186 W/m (pile A) and 201 W/m (pile B) while cooling. This attained the author’s expectations (160 W/m per pile). Here, the COP for ASHP was calculated from the air temperature measured at the experimental site and the performance curve of a typical ASHP. The COPs for this system (GSHP) and ASHP are shown in Fig. 11. The average COPs for this system and ASHPs were 4.89 and 2.90 while cooling respectively. Thus, this system is about 1.7 times more efficient than the more common ASHP systems.

6/16 6/18 6/20 6/22 6/24 6/26 6/28 6/30 7/2 7/4 7/6 7/8 7/10 7/12 7/14 7/16 7/18 7/20 7/22 7/24 7/26 7/28 7/30 8/1 8/3 8/5 8/9 8/11 8/13 8/15 8/17 8/19 8/21 8/23 8/25 8/27 8/29 8/31 9/2 9/4 9/6 9/8 9/10

10

15

20

25

30

Temperature [°C] 35

40

Figure 8:Heat rejection into the ground in 2004

Air-T emperature

Heat Sink Water T emperature

Figure 9:Air temperature and heat sink water temperature in 2004 6/16 6/18 6/20 6/22 6/24 6/26 6/28 6/30 7/2 7/4 7/6 7/8 7/10 7/12 7/14 7/16 7/18 7/20 7/22 7/24 7/26 7/28 7/30 8/1 8/3 8/5 8/9 8/11 8/13 8/15 8/17 8/19 8/21 8/23 8/25 8/27 8/29 8/31 9/2 9/4 9/6 9/8 9/10

0

50

100

150

200

250

300

Heat Rejection into The Ground (Pile B) [W/m]

6/16 6/18 6/20 6/22 6/24 6/26 6/28 6/30 7/2 7/4 7/6 7/8 7/10 7/12 7/14 7/16 7/18 7/20 7/22 7/24 7/26 7/28 7/30 8/1 8/3 8/5 8/9 8/11 8/13 8/15 8/17 8/19 8/21 8/23 8/25 8/27 8/29 8/31 9/2 9/4 9/6 9/8 9/10

0

50

100

150

200

250

300

Heat Rejection into The Ground (Pile A) [W/m]

8 6 4

COP

2 6/16 6/18 6/20 6/22 6/24 6/26 6/28 6/30 7/2 7/4 7/6 7/8 7/10 7/12 7/14 7/16 7/18 7/20 7/22 7/24 7/26 7/28 7/30 8/1 8/3 8/5 8/9 8/11 8/13 8/15 8/17 8/19 8/21 8/23 8/25 8/27 8/29 8/31 9/2 9/4 9/6 9/8 9/10

0

Figure 10:COP change for cooling in 2004 10 9

GSHP

8 7

COP

6 5 4 3 2 ASHP

1 0 6/2

6/22

7/12

8/1

8/21

9/10

9/30

Figure 11:Units COP

6.

EXAMINATION OF CONSTRUCTION COST

A comparison of the construction cost between the usual borehole system and our proposed system is shown in Table 2. Here, a single U-tube is assumed to be used in the usual borehole system. The heat extraction and rejection per unit length of a single U-tube is assumed to be 40 W/m. The boring cost is ordinarily ¥10,000/m (approx. US$100/m) in Japan. The heat extraction and rejection capabilities of the proposed system are based on the cooling experiment performed in 2004. The construction cost for the proposed system is based on an example introduced in an actual building. The cost of construction per heat extraction and rejection unit of the proposed system is 90 percent cheaper than that of a borehole system. Accordingly, the proposed system is expected to pay for itself within ten years.

Table 2:Comparison of Cost

(Single U-tube)

Proposed system (Cast-in-place concrete pile type) (8 pairs of U-tubes)

Heat extraction and rejection per unit of heat exchange [W/m]

40

200

Boring costs [¥/m]

10,000

-

Piping costs [¥/m]

2,000

2,610

Additional labor costs for foundation & piling work [¥/m]

-

3,540

Total cost [¥/m]

12,000

6,150

Total cost per extraction and rejection heat unit [¥/W]

300

30

Form of heat exchange

7.

Borehole type

CONCLUSION

(1) The authors have developed a GSHP system using the cast-in-place concrete pile foundations of a building as heat exchangers in order to reduce the initial boring cost. (2) In this system, eight U-tubes are arranged around the outer surface of cast-in-place concrete pile foundations. (3) The heat exchange capability of this system, the subterranean temperature change and performance of the heat pump were investigated in a full-scale experiment. (4) The average values for heat rejection were 186~201 W/m (per pile, 25 W/m per pair of tubes) while cooling. (5) The average COP for this system was 4.89 while cooling, so this system is about 1.7 times more efficient than the more common ASHP system. (6) The initial cost of construction per heat extraction and rejection unit is ¥30/W (approx. US$0.30/W) for this system, whereas it is ¥300/W (US$3/W) for the standard borehole system. (7) This system is expected to be commercially viable. (8) As to operational problem related this approach, the amount of work to connect U-tube to reinforcing bar cannot be disregarded. The simplification of the construction method will be examined as the future research. (9) The results in this experiment of this research were obtained at a certain local site. A lot of other research works will be required in the future in order to develop this system to apply to a real office building generally.

REFERENCES Arup Geotechnics, 2002. DTI Partners in Innovation 2002. Ground Storage of Building Heat Energy. Overview Report. Hamada, Y., K. Ochifuji, K. Nagano, and M. Nakamura. 1997. Study on the heating and cooling by long-term heat storage with underground vertical U-tubes. MEGASTOCK’97, Proceedings. Vol. 1, pp. 37-42. Kavanaugh, S.P. 1992. Field test of a vertical ground-coupled heat pump in Alabama. ASHRAE Transactions. Vol. 98 (2), pp. 607-615. Kavanaugh, S.P., K. Rafferty. 1997. Ground-source heat pumps, Design of geothermal systems for commercial and institutional buildings. Atlanta: American Society of Heating, Refrigerating, and Air-Conditioning Engineers, Inc. Presetschnik, A.., H, Huber. 2005. Analysis of a ground ground coupled heat pump heating and cooling system for a multi-story office building. 8th International Energy Agency, HEAT PUMP CONFERENCE 2005, Proceedings. p4-8.

B. Background - Semantic Scholar

Platinum measurement resistor (±0.5°C). In the pipe. Water flow. Flow meter (±2%). In the pipe. Electrical power used. Electric power meter. Power panel. Outside temperature, relative humidity, wind velocity, wind direction, quantity of solar radiation, rainfall. 4. COOLING AND HEATING RESULTS IN 2003. 4.1 Underground ...

437KB Sizes 0 Downloads 337 Views

Recommend Documents

B. Background - Semantic Scholar
system employs the foundation piles of buildings as heat exchanger (so called “energy pile system”) is introduced into some buildings in order to reduce the initial boring cost (Hamada et al 1997; Arup Geotechnics 2002;. Presetschnik et al 2005).

Foreground-Background Regions Guided ... - Semantic Scholar
ent values and found that k = 0.34 gives the best results, but Sauvola[2] ... The suitable range for θ is from -45 to 45 degrees. From these ranges, a set of filters is generated for different .... International Conference on Computer Analysis of Im

Art - Blakemore (B) - Semantic Scholar
To achieve this, some kind of central monitor6 or internal 'forward model'4,5 ..... Wellcome Trust four-year Ph.D. Programme in Neuroscience at University College. London. articles. Fig. .... 183–242 (Academic, San Diego,California 1997). 31.

B Biometric Paradigm Using Visual Evoked Potential - Semantic Scholar
Applica- tions for this biometric system include high security systems. (access to classified documents, defence applications) where fingerprints and other identity ...

B Biometric Paradigm Using Visual Evoked Potential - Semantic Scholar
University of Essex, UK ... presence of mobile phone cameras, digital cameras, and wireless video .... Vector Quantizer network (LVQ) was used to classify AR.

Physics - Semantic Scholar
... Z. El Achheb, H. Bakrim, A. Hourmatallah, N. Benzakour, and A. Jorio, Phys. Stat. Sol. 236, 661 (2003). [27] A. Stachow-Wojcik, W. Mac, A. Twardowski, G. Karczzzewski, E. Janik, T. Wojtowicz, J. Kossut and E. Dynowska, Phys. Stat. Sol (a) 177, 55

Physics - Semantic Scholar
The automation of measuring the IV characteristics of a diode is achieved by ... simultaneously making the programming simpler as compared to the serial or ...

Physics - Semantic Scholar
Cu Ga CrSe was the first gallium- doped chalcogen spinel which has been ... /licenses/by-nc-nd/3.0/>. J o u r n a l o f. Physics. Students http://www.jphysstu.org ...

Physics - Semantic Scholar
semiconductors and magnetic since they show typical semiconductor behaviour and they also reveal pronounced magnetic properties. Te. Mn. Cd x x. −1. , Zinc-blende structure DMS alloys are the most typical. This article is released under the Creativ

vehicle safety - Semantic Scholar
primarily because the manufacturers have not believed such changes to be profitable .... people would prefer the safety of an armored car and be willing to pay.

Reality Checks - Semantic Scholar
recently hired workers eligible for participation in these type of 401(k) plans has been increasing ...... Rather than simply computing an overall percentage of the.

Top Articles - Semantic Scholar
Home | Login | Logout | Access Information | Alerts | Sitemap | Help. Top 100 Documents. BROWSE ... Image Analysis and Interpretation, 1994., Proceedings of the IEEE Southwest Symposium on. Volume , Issue , Date: 21-24 .... Circuits and Systems for V

TURING GAMES - Semantic Scholar
DEPARTMENT OF COMPUTER SCIENCE, COLUMBIA UNIVERSITY, NEW ... Game Theory [9] and Computer Science are both rich fields of mathematics which.

A Appendix - Semantic Scholar
buyer during the learning and exploit phase of the LEAP algorithm, respectively. We have. S2. T. X t=T↵+1 γt1 = γT↵. T T↵. 1. X t=0 γt = γT↵. 1 γ. (1. γT T↵ ) . (7). Indeed, this an upper bound on the total surplus any buyer can hope

i* 1 - Semantic Scholar
labeling for web domains, using label slicing and BiCGStab. Keywords-graph .... the computational costs by the same percentage as the percentage of dropped ...

fibromyalgia - Semantic Scholar
analytical techniques a defect in T-cell activation was found in fibromyalgia patients. ..... studies pregnenolone significantly reduced exploratory anxiety. A very ...

hoff.chp:Corel VENTURA - Semantic Scholar
To address the flicker problem, some methods repeat images multiple times ... Program, Rm. 360 Minor, Berkeley, CA 94720 USA; telephone 510/205-. 3709 ... The green lines are the additional spectra from the stroboscopic stimulus; they are.

Dot Plots - Semantic Scholar
Dot plots represent individual observations in a batch of data with symbols, usually circular dots. They have been used for more than .... for displaying data values directly; they were not intended as density estimators and would be ill- suited for

Master's Thesis - Semantic Scholar
want to thank Adobe Inc. for also providing funding for my work and for their summer ...... formant discrimination,” Acoustics Research Letters Online, vol. 5, Apr.

talking point - Semantic Scholar
oxford, uK: oxford university press. Singer p (1979) Practical Ethics. cambridge, uK: cambridge university press. Solter D, Beyleveld D, Friele MB, Holwka J, lilie H, lovellBadge r, Mandla c, Martin u, pardo avellaneda r, Wütscher F (2004) Embryo. R

Physics - Semantic Scholar
length of electrons decreased with Si concentration up to 0.2. Four absorption bands were observed in infrared spectra in the range between 1000 and 200 cm-1 ...

aphonopelma hentzi - Semantic Scholar
allowing the animals to interact. Within a pe- riod of time ranging from 0.5–8.5 min over all trials, the contestants made contact with one another (usually with a front leg). In a few trials, one of the spiders would immediately attempt to flee af

minireviews - Semantic Scholar
Several marker genes used in yeast genetics confer resis- tance against antibiotics or other toxic compounds (42). Selec- tion for strains that carry such marker ...

PESSOA - Semantic Scholar
ported in [ZPJT09, JT10] do not require the use of a grid of constant resolution. We are currently working on extending Pessoa to multi-resolution grids with the.